PoliticsTop StoryUS

Maryland officials release timeline, cost estimate, for rebuilding bridge

Maryland plans to rebuild the Francis Scott Key Bridge in just over four years at an estimated cost between $1.7 billion and $1.9 billion, a state transportation official said Thursday. As salvage efforts continue, authorities also announced late Wednesday they had recovered the body of a fifth person who died in the March 26 collapse.

Quick Read

  • Maryland Bridge Rebuild Plan: Maryland officials plan to rebuild the Francis Scott Key Bridge by fall of 2028, with an estimated cost between $1.7 billion and $1.9 billion, as stated by David Broughton, a spokesperson for the Maryland Department of Transportation.
  • Fatal Collapse and Recovery Efforts: Following the tragic collapse on March 26, which resulted in the deaths of six roadwork crew members, authorities have recently recovered the body of the fifth victim, Miguel Angel Luna Gonzalez.
  • Victim Identification: All victims of the collapse were Latino immigrants from Mexico, Guatemala, El Salvador, and Honduras. Governor Wes Moore extended condolences and highlighted the ongoing community support for the victims’ families.
  • Insurance Payouts and Financial Aspects: The bridge’s insurance policy broker confirmed a $350 million payout to the state of Maryland by Chubb, with more expected as the situation develops.
  • Salvage Operations: Salvage efforts are ongoing, including plans to refloat and remove the Dali container ship, which has been stationary at the collapse site, to resume maritime traffic through Baltimore’s port by May 10.
  • Demolition and Cleanup: Crews are preparing for a controlled demolition to remove the largest remaining span of the bridge, with operations involving the country’s largest hydraulic grabber and one of the largest cranes on the Eastern Seaboard to manage debris and clear the site.

The Associated Press has the story:

Maryland officials release timeline, cost estimate, for rebuilding bridge

Newslooks- ANNAPOLIS, Md. (AP) —

Maryland plans to rebuild the Francis Scott Key Bridge in just over four years at an estimated cost between $1.7 billion and $1.9 billion, a state transportation official said Thursday. As salvage efforts continue, authorities also announced late Wednesday they had recovered the body of a fifth person who died in the March 26 collapse.

The state plans to build a new span by fall of 2028, said David Broughton, a spokesman for the Maryland Department of Transportation. He said the cost estimate is preliminary, and detailed engineering specifics have not been confirmed.

Flowers are seen at a memorial site to honor the construction workers who lost their lives in the collapse of the Francis Scott Key Bridge in Baltimore, Thursday, April 25, 2024. (AP Photo/Matt Rourke)

Late Wednesday, authorities announced they recovered the body of a fifth person who was missing after the collapse of the bridge more than a month ago, shutting down the port of Baltimore, one of the busiest ports in the country.

Six members of a roadwork crew plunged to their deaths on March 26 when a container ship lost power and crashed into one of the bridge’s supporting columns. The Key Bridge Response Unified Command announced that the victim found Wednesday was identified as Miguel Angel Luna Gonzalez, 49, of Glen Burnie, Maryland. All of the victims were Latino immigrants who came to the United States from Mexico, Guatemala, El Salvador and Honduras.

“We continue to pray for Miguel Angel Luna Gonzalez, his family and all those who love him, acknowledging the anguish they have experienced since the Key Bridge collapsed,” Gov. Wes Moore said in a statement Thursday. “We pray for comfort, we pray for healing, and we pray for peace in knowing that their loved one has finally come home.”

Roberto Marquez, an artist from Dallas, speaks during an interview with the Associated Press at a memorial site to honor the construction workers who lost their lives in the collapse of the Francis Scott Key Bridge in Baltimore, Thursday, April 25, 2024. (AP Photo/Matt Rourke)

Salvage teams found one of the missing construction vehicles Wednesday and notified the Maryland State Police, officials said. State police investigators and Maryland Transportation Authority Police officers and the FBI responded to the scene and recovered the body inside a red truck. The state police underwater recovery team and crime scene unit also assisted.

Meanwhile, the broker for the bridge’s insurance policy confirmed Thursday that a $350 million payout will be made to the state of Maryland in what is expected to be the first of many payouts related to the collapse.

Chubb, the company that insured the bridge, is preparing to make the $350 million payment, according to WTW, the broker. Douglas Menelly, a spokesperson for WTW, on Thursday confirmed plans for the payout, which was first reported by The Wall Street Journal. Chubb did not immediately respond to a request for comment Thursday.

Workers remove wreckage of the collapsed Francis Scott Key Bridge, Thursday, April 25, 2024, in Baltimore. (AP Photo/Matt Rourke)

The Maryland Transportation Authority said Thursday that the state’s treasurer filed a claim on the day of the bridge’s collapse “against our $350 million property policy and put on notice our $150 million liability policy first tier carrier on behalf of MDTA.”

“We expect the full property policy to be paid very shortly,” the agency said in a news release.

The Dali container ship has been stationary amid the wreckage since the collapse, but crews plan to refloat and remove the ship, allowing more maritime traffic to resume through Baltimore’s port. Officials expect to have it removed by May 10, according to a Port of Baltimore news release.

Salvage and demolition crews were still working around the clock to clear wreckage from the collapse site. They’re now focused primarily on freeing the Dali from a massive steel span that came crashing down on the ship’s bow.

Workers remove wreckage of the collapsed Francis Scott Key Bridge, Thursday, April 25, 2024, in Baltimore. (AP Photo/Matt Rourke)

That will allow the ship to be refloated and guided back into the Port of Baltimore. It will also allow most maritime traffic to resume through the busy East Coast port.

On Thursday morning, crews were preparing for a controlled demolition that will break down the largest remaining span and send it tumbling into the water. Then a massive hydraulic grabber will lift the resulting sections of steel onto barges.

The hydraulic grabber, which officials have called the largest in the country, was also in motion Thursday morning. Moving ever so slowly, the giant claw descended into the depths of the Patapsco River and emerged with a steel beam in its trusses. It was operating in tandem with the Chesapeake 1000, one of the largest cranes on the Eastern Seaboard.

Read more U.S. news

Previous Article
US Military: Airstrike targeting al-Qaida leader in Syria killed a farmer May 2023
Next Article
IRS acts to address wide disparity in audit rates between Black taxpayers, other filers

How useful was this article?

Click on a star to rate it!

Average rating 0 / 5. Vote count: 0

No votes so far! Be the first to rate this article.

Latest News

Menu